Roof Ice Melt Recommended Specifications
Download the PDF version.
Part 1 - General
References:
Requirements of the General Conditions, Supplementary Conditions
and Section
Section Includes:
-
Roof Ice Melt (RIM) System Materials and Components. RIM
System designs shall be supplied for Class 1 Area - Large
Snow Load Accumulation Areas and RIM2 System designs
shall be supplied for Class 2 Area - Moderate Snow Load
Accumulation Areas.
-
Heated Gutters and Downspouts shall use 12 w/ft SRH
heating cable for Class 1 Areas and 8 w/ft WFP heating
cable for Class 2 and Class 3 Areas.
-
This project is in a
Class (Select 1, 2 or 3) Snow Load Accumulation Area.
-
Control
System including panel enclosure, ground fault branch circuit
protection, temperature controllers, branch switching devices,
power on lights and accessories.
Related Work In Other Sections
- Section _ _ _ _ _: Roof
Design Details
- Section _ _ _ _ _: Gutter
and Downspout Details
Quality Assurance
-
The RIM System, SRH / WFP Heating Cables and Control Panel
shall be manufactured and supplied in conformance with Bylin
Engineered System's quality assurance program.2
-
The manufacturer
shall have at least ten (10) years experience in the design
and supply of Roof and Gutter De-Icing Systems.
-
Submittals
-
Furnish detail drawings showing layouts for each
RIM Section and its corresponding heated gutter and
downspout, cross section drawings, control panel drawings,
and installation and operation instructions.
-
Furnish Installation Check-Out
Forms to be completed after the installation is finished.
-
Product
Delivery, Storage And Handling
-
RIM System Equipment, SRH
/ WFP Heating Cables and Control Panel shall be delivered
in undamaged condition. The
jobsite supervisor will inspect the materials when delivered
and notify the trucking company and manufacturer of any
damage within 24 hours of receipt of materials.
Warranty
-
The SRH / WFP Heating Cables shall be warrantied against
defects in material and workmanship for a period of ten (10)
years from date of final acceptance.
-
The Control Panel components
shall be warranted against defects in material and workmanship
for a period of one (1) year from date of acceptance.
-
The
manufacturer, at his option, shall either repair or supply
replacement materials if that material is defective per
the above warranty definitions.
Part 2 - Products
Roof Ice Melt (RIM) System
-
Custom engineered RIM System manufactured by Bylin Engineered
Systems, 4800 Golden Foothill Parkway El Dorado Hills, CA,
(1-888-313-5666).
-
RIM and RIM2 Cover Panels to be 20oz copper
or 40 mil aluminum with Kynar-based paint finish.
-
SRH /
WFP Heating Cable
-
The RIM Eave Panel shall contain 3 runs of 12 w/ft SRH
self-regulating heating cable per foot of eave. The
RIM Valley Panel shall contain 2 runs of 12 w/ft SRH self-regulating
heating cable. RIM2 Eave Panel shall contain 2 runs
of 8 w/ft WFP-622(612) self-regulating heating cable per
foot of eave. The RIM2 Valley Panel shall contain
2 runs of 8 w/ft WFP-622(612) self-regulating heating
cable.
-
The
heating cable shall be UL and CSA listed specifically
as electric roof and gutter de-icing and snow-melting equipment.
-
The
heating cable shall be of parallel resistance construction
capable of being cut to length and terminated in the
field.
-
The heating cable shall consist of two parallel nickel-plated
copper bus wires embedded in a radiation cross-linked
self-regulating conductive polymer core specifically
designed for snow and ice melting. The heating cable shall be capable
of varying its heat output along its entire length. The
heating cable shall include a polyolefin dielectric jacket
rated 300 VAC at 105°C, a tinned-copper braid (14
AWG equivalent wire size), and a UV stabilized polyolefin
overjacket.
-
The heating cable output in snow and ice at
32°F
shall be 12 w/ft for SRH heating cable and 8 w/ft for
WFP heating cable.
-
SRH / WFP Heating Cable supplied by Bylin
Engineered Systems, El Dorado Hills, CA (1-888-313-5666).
Control Panel
-
The Control System shall include either a High Efficiency
Control Panel (HECS) or Manual/Automatic Control Panel (MACS)
complete with branch circuit protection, ground fault protection,
ambient temperature controller, RIM Eave Panel temperature
controllers, solid state relays, terminal blocks, switches,
power on light and accessories.
-
Control Panel supplied by
Bylin Engineered Systems, El Dorado Hills, CA (1-888-313-5666).
-
Junction
Box / Power Termination
-
The heating cable circuits shall
be connected to the power wiring in an approved junction
box with approved termination components.
Part 3 - Execution
Inspection:
The Contractor shall inspect the materials supplied against the Packing List
and Design and Installation Manual. The Contractor shall note any discrepancies
and work with the manufacturer to resolve.
Section Includes:
-
The RIM System, SRH / WFP Gutter / Downspout Heating System
and Control Panel shall be installed in accordance with
the manufacturer's Design and Installation Manual. Any
deviations shall be reviewed and approved by the manufacturer.
-
Coordinate
with the RIM System and SRH / WFP heating cable installers,
the gutter and downspout installers and the control panel
wiring and section conduit and junction box wiring installers.
-
The
electrical contractor shall test the SRH / WFP heating
cables, complete the Installation Test Forms and submit them
to Bylin Engineered Systems for review and approval.
|